Moorlands Park Project

Staff Contact


Ann Stanton
Parks Project Manager
(425) 398-8900
 

Updates:

 

October 1, 2017 Progress Report:

 

 

     

 

 

Play equipment is going in during the first part of October!  In addition, paving pathways, installation of the restroom, picnic shelter and backstop are also scheduled for October.  Finishing grading, irrigation, grass seeding, and planting will be underway as well, weather permitting.  Construction is approaching completion at last.

 

September 1, 2017 Progress Report:

 

 

 

 

Moorlands Park has seen major work this summer, but most of it is underground: power, water, sewer, conduit for cable, storm drains, footings and building subgrades.  The temporary path between the school and church drop-off points was readied this week for school's start next Wednesday.  The concrete sidewalk along 84th is being formed for concrete now, to be poured next week.  Park pathways have been cut to grade.  The park has passed inspection for its sewer and water installations, storm drainage is mostly in, the ballfield fenceposts are going up and the play area storm drainage is going in this week.  Once that is in, work will begin on the play equipment in several stages including footings, play surfacing and equipment installation.  Thank you for your patience; the park will be a noisy place for two-plus months more.

 

Schedule:

·         Public review of Proposed Park Design: Open House Wednesday, October 5, 2016 at Moorlands Elementary.

·         City Council approved the updated Park Master Plan on November 21, 2016.

·         Permit application and review: November 2016 to March 2017.

·         Construction bid awarded: June 12, 2017

·         Park is closed to the public during construction: late November 2017

·         A-1 Landscaping and Construction awarded the construction contract on June 12, 2017.

·         Construction began June 28, 2017.

·         Utilities installed June through August.

·         Construction Completion: late November 2017 (anticipated)

·         Park open to public: December, 2017

·         Ballfield open to public use: January 2019

Background:

Moorlands Park was first established as a neighborhood park in the 1940's. It was transferred to the city from King County Parks in 2002 following Kenmore’s incorporation. The City of Kenmore prepared a park master plan in 2006. 

·         Moorlands Park Master Plan Adopted 2006

·         2006 Summary Report

Project Description:

The Moorlands Park renovation will construct park improvements, including ballfield renovation, new picnic shelter, perimeter path and play area upgrades.

·         2016 Concept Plan

·         Play Area Design Concept

·         Proposed Play Equipment

 

Funding:

The Capital Improvement Program project budget is $2,190,020. The City received funding assistance of $637,520 from the Washington State Recreation and Conservation Office.

 

 

 

Last updated: Fri, 09/29/2017 - 10:21am